Sprint 11: 24-Jul-2010 to 7-Aug-2010

Effort available:

  • GK: 6 days
  • BW: 4.5 days

Project outline plan: ADMIRAL planning

Previous sprint: ADMIRAL SprintPlan 10

Sprint Dates Effort Plan Planning meeting Review meeting
Sprint 11 24 Jul - 7 Sep 9 days sprint 11 plan sprint 11 planning sprint 11 review

Current milestone

The next goal for the project is to complete the functions covered by phase 1 of the project plan by the end of October, with front-to-back submission of research datasets to the library databank repository service, and providing visible web-based feedback to our research partners of the submitted datasets. This we intend to use as the basis for iterative improvements and enhancements in phase 2 of the project, with the researchers guiding us concerning what constitutes useful metadata to capture and expose with the submitted datasets.

Outstanding items from phase 1 of project plan:

Date WP Activity Milestone and/or deliverable
Jan-2010 WP2 Annotation requirements gathering (use data audits as starting point). Focus on annotations that can support archiving and retrieval (see WP3) (10d) Identified initial data set annotations to implement, and potential vocabularies
Feb-2010 WP1 Security model review Reviewed/updated trust, threat and security model
WP2 Pair-programmed implementation of Shuffl plug-in for annotating user data, and demonstrate these to research users as soon as possible (10d) Initial implementation of at least 1 Shuffl plug-in for data annotation, and user feedback
Mar-2010 WP3 Survey and select format and vocabularies for bundling datasets with annotations (considering what can be accepted by OULS). (10d) Identified data format(s) and administrative vocabularies to be used for bundling datasets with annotations
WP3 Check metadata coverage of selected data format/vocabularies with research users – articulate retrieval use-cases (10d). Identified domain vocabularies to be used for bundling datasets with annotations
WP4 Discuss submission requirements with research partners, OULS and CLARION teams (5d). Agreed publication embargo policies with research users, on a case-by-case basis.
Apr-2010 WP3 Create packaging tools to create bundles for submission to OULS databank. Test use of packaging tools applied to real data (10d). Initial implementation of tooling to create archival submission packages from datasets, Shuffl annotations.
WP4 Initial implementation of submission tools – e.g. SWORD protocol client (10d). Initial submission tools.
May-2010 WP3 Refine submission package tooling based on user feedback. Work with users to create archive submission packages for selected datasets. (10d) Data packages ready for repository submission
WP4 Review submission tools with partners and users, including selection of embargo policies (5d).
WP4 Refine submission tools (5d). Submission tools ready for use.
WP4 Configure Databank to implement embargo policies (OULS – 10d)
Jun-2010 WP3 Review and publish documentation and training materials for packaging tools (5d) Stable, published user documentation
WP4 Perform and debug initial submissions from shared file system (10d) Initial submissions from LSDS to data repository.
WP4 Review and publish documentation and training materials for submission tools (5d) Stable, published user documentation

Outline goals

For the next sprint, we aim to:

  • review, debug and update documentation for the ADMIRAL system scripted creation procedure
  • create a new ADMIRAL file sharing deployment for the evolutionary development group
  • file sharing system bug fixes (password over unencrypted HTTP channel; https access reporting server configuration error)
  • Progress RDF creation using Shuffl

Working towards:

  • Front-to-back, researcher-to-repository, test deployment
  • Capture dataset description as RDF
  • Package data+description and submit to Databank test system

Planned activities and user stories

See: ADMIRAL_PlanMeeting_11

Task breakdown

(See planning notes - ADMIRAL_PlanMeeting_11)

Review of planning process

We have planned a short sprint with immediate goals only. The planning process has focussed on identifying priority tasks in the current work schedule, and building momentum around them.