Sprint 1: 1-Dec-2009 to 31-Dec-2009

Effort:

  • GK: 12 days

Project outline plan: ADMIRAL planning

Previous sprint: ADMIRAL SprintPlan 0

Current milestone

Date WP Activity Milestone and/or deliverable
Dec-2009 WP0 Sprint planning and review Sprint plans and retrospectives
WP0 Recruitment Position offered
WP0 Set up project infrastructure (5d) Project version management, wiki, blog, discussion list in place. Project summary description and initial plans published.
WP1 Survey networked/web file system options. Survey authentication mechanisms and single-sign-on integration of networked file system. Discussion with colleagues at Cambridge. (10d) Selected platform and software for LSDS

Outline goals

The main tasks for this sprint are to get the project up-and-running:

  • WP0: Sprint plan
  • WP0: Recruitment
  • WP0: Project infrastructure (version management, wiki, blog, discussion list).
  • WP1: LSDS surveyand component selection
  • WP9: Data audits

Planned activities and user stories

WP Activity Effort est Effort actual Description Target date Actual date
WP0 0.1 1.4 -.-- Misc admin (ongoing) --
0.2 1.00 0.2 General project management (ongoing) --
0.3 0.25 0.2 Sprint 1 plan 01-Dec-2009 14-Dec-2009
0.4 0.25 -- Sprint 1 review 31-Dec-2009 04-Jan-2010
0.5 0.50 0.50 Project meeting 14-Dec-2009 14-Dec-2009
0.6 3.0 2.7 Recruitment 31-Dec-2009 31-Dec-2009
0.7 5.0 -.-- Project infrastructure 31-Dec-2009 (ongoing)
WP1 1.0 5.0 0.6 File sharing survey 31-Dec-2009 (ongoing)
1.1 2.0 0 Authentication support survey 31-Dec-2009 (outstanding)
1.2 1.0 0.2 Discussion with CLARION project 31-Dec-2009 09-Dec-2009
1.3 1.0 0 Discussion with local IT support 31-Dec-2009 (outstanding)
WP9 9.0 0.0 0 Data audits 31-Dec-2009 (ongoing)

Task breakdown

(n/a this sprint)

Sprint review notes

Somewhat slow getting up to speed because of overhang from previous projects, and time off.

Wiki and blog are in place. I'll hold off creating discussion list and version management until they are needed: then I'll have a better idea of requirements.

One interesting thing came out of the meeting with John Pybus: the Neurocommons project has some file sharing requirements similar to ADMIRAL - John said he'd try and bring us together for a brainstorming session early in 2010.

Retrospective

Many distractions from other projects - ADMIRAL effort applied has been somewhat diffuse.

Recruitment achieved: position offered and accepted.

Initial project wiki, blog and project management framework in place. Creating task effort summary is awkward - look for a way to improve this.

Some progress made on LSDS survey, but not completed as planned. The number of options to be surveyed seems fewer than at first anticipated; a file sharing system based mainly on standard Linux tools seems to be the most promising option (cf. ADMIRAL_LSDS_requirements_and_survey).

Data audits: questionnaire, presentation and introduction to project have been prepared. Invitations issued to the four test user groups for initial meetings; have heard back with dates from two of these.

Velocity

Task estimated effort completed / effort spent:

Activity summary

Tuesday, 1 December, 2009
(0.5) Short-list applicants (task 0.6)
Wednesday, 2 December, 2009
(0.2) Prepare interview questions (task 0.6)
(0.3) Set up project planning and sprint planning framework in wiki (task 0.7)
Tuesday, 8 December, 2009
(0.8) Interviews and initial review (task 0.6)
Wednesday, 9 December, 2009
(0.3) Review interview candidiates (task 0.6)
(0.2) CLARION project discussion embargo issues (Jim Downing, Brian Brookes) (task 1.2)
(0.3) General email (task 0.1)
Friday, 11 December, 2009
(0.1) Related work notes started in wiki (task 1.0) - see ADMIRAL related work
(0.1) Agile ecosystem notes in wiki (task 0.2) - see ADMIRAL agile ecosystem and project procedures
(0.1) Initial LSDS survey notes in wiki (task 1.0) - see ADMIRAL LSDS requirements
Monday, 14 December, 2009
(0.3) General email - esp. HTML5 metadata issues (task 0.1)
(0.2) Sprint plan (task 0.3)
(0.5) Project meeting and follow-up (task 0.5)
Tuesday, 15 December, 2009
(0.5) Survey options for LSDS, ask for meetings with John Pybus and Simon Ellis (task 1.0)
(0.2) Review JISC JISC Deposit Expose and Discover call - first pass (task 0.1)
(0.1) Register objection to Microdata inclusion in HTML5 core (task 0.1)
Wednesday, 16 December, 2009
(0.6) Preparing for second (working) interview (task 0.6)
Thursday, 17 December, 2009
(0.7) Recruitment (incl preparation) (task 0.6)
(0.1) Admin (task 0.1)
Friday, 18 December, 2009
(0.1) Recruitment: offer made (task 0.6)
(0.4) Response to JISC Deposit Expose and Discover call (task 0.1)
(0.1) General admin (task 0.1)
Wednesday, 23 December, 2009
(0.5) Meeting with John Pybus (task 1.0)