Sprint 1: 1-Dec-2009 to 31-Dec-2009
Effort:
- GK: 12 days
Project outline plan: ADMIRAL planning
Previous sprint: ADMIRAL SprintPlan 0
Current milestone
| Date | WP | Activity | Milestone and/or deliverable |
|---|---|---|---|
| Dec-2009 | WP0 | Sprint planning and review | Sprint plans and retrospectives |
| WP0 | Recruitment | Position offered | |
| WP0 | Set up project infrastructure (5d) | Project version management, wiki, blog, discussion list in place. Project summary description and initial plans published. | |
| WP1 | Survey networked/web file system options. Survey authentication mechanisms and single-sign-on integration of networked file system. Discussion with colleagues at Cambridge. (10d) | Selected platform and software for LSDS |
Outline goals
The main tasks for this sprint are to get the project up-and-running:
- WP0: Sprint plan
- WP0: Recruitment
- WP0: Project infrastructure (version management, wiki, blog, discussion list).
- WP1: LSDS surveyand component selection
- WP9: Data audits
Planned activities and user stories
| WP | Activity | Effort est | Effort actual | Description | Target date | Actual date |
|---|---|---|---|---|---|---|
| WP0 | 0.1 | 1.4 | -.-- | Misc admin | (ongoing) | -- |
| 0.2 | 1.00 | 0.2 | General project management | (ongoing) | -- | |
| 0.3 | 0.25 | 0.2 | Sprint 1 plan | 01-Dec-2009 | 14-Dec-2009 | |
| 0.4 | 0.25 | -- | Sprint 1 review | 31-Dec-2009 | 04-Jan-2010 | |
| 0.5 | 0.50 | 0.50 | Project meeting | 14-Dec-2009 | 14-Dec-2009 | |
| 0.6 | 3.0 | 2.7 | Recruitment | 31-Dec-2009 | 31-Dec-2009 | |
| 0.7 | 5.0 | -.-- | Project infrastructure | 31-Dec-2009 | (ongoing) | |
| WP1 | 1.0 | 5.0 | 0.6 | File sharing survey | 31-Dec-2009 | (ongoing) |
| 1.1 | 2.0 | 0 | Authentication support survey | 31-Dec-2009 | (outstanding) | |
| 1.2 | 1.0 | 0.2 | Discussion with CLARION project | 31-Dec-2009 | 09-Dec-2009 | |
| 1.3 | 1.0 | 0 | Discussion with local IT support | 31-Dec-2009 | (outstanding) | |
| WP9 | 9.0 | 0.0 | 0 | Data audits | 31-Dec-2009 | (ongoing) |
Task breakdown
(n/a this sprint)
Sprint review notes
Somewhat slow getting up to speed because of overhang from previous projects, and time off.
Wiki and blog are in place. I'll hold off creating discussion list and version management until they are needed: then I'll have a better idea of requirements.
One interesting thing came out of the meeting with John Pybus: the Neurocommons project has some file sharing requirements similar to ADMIRAL - John said he'd try and bring us together for a brainstorming session early in 2010.
Retrospective
Many distractions from other projects - ADMIRAL effort applied has been somewhat diffuse.
Recruitment achieved: position offered and accepted.
Initial project wiki, blog and project management framework in place. Creating task effort summary is awkward - look for a way to improve this.
Some progress made on LSDS survey, but not completed as planned. The number of options to be surveyed seems fewer than at first anticipated; a file sharing system based mainly on standard Linux tools seems to be the most promising option (cf. ADMIRAL_LSDS_requirements_and_survey).
Data audits: questionnaire, presentation and introduction to project have been prepared. Invitations issued to the four test user groups for initial meetings; have heard back with dates from two of these.
Velocity
Task estimated effort completed / effort spent:
Activity summary
- Tuesday, 1 December, 2009
- (0.5) Short-list applicants (task 0.6)
- Wednesday, 2 December, 2009
- (0.2) Prepare interview questions (task 0.6)
- (0.3) Set up project planning and sprint planning framework in wiki (task 0.7)
- Tuesday, 8 December, 2009
- (0.8) Interviews and initial review (task 0.6)
- Wednesday, 9 December, 2009
- (0.3) Review interview candidiates (task 0.6)
- (0.2) CLARION project discussion embargo issues (Jim Downing, Brian Brookes) (task 1.2)
- (0.3) General email (task 0.1)
- Friday, 11 December, 2009
- (0.1) Related work notes started in wiki (task 1.0) - see ADMIRAL related work
- (0.1) Agile ecosystem notes in wiki (task 0.2) - see ADMIRAL agile ecosystem and project procedures
- (0.1) Initial LSDS survey notes in wiki (task 1.0) - see ADMIRAL LSDS requirements
- Monday, 14 December, 2009
- (0.3) General email - esp. HTML5 metadata issues (task 0.1)
- (0.2) Sprint plan (task 0.3)
- (0.5) Project meeting and follow-up (task 0.5)
- Tuesday, 15 December, 2009
- (0.5) Survey options for LSDS, ask for meetings with John Pybus and Simon Ellis (task 1.0)
- (0.2) Review JISC JISC Deposit Expose and Discover call - first pass (task 0.1)
- (0.1) Register objection to Microdata inclusion in HTML5 core (task 0.1)
- Wednesday, 16 December, 2009
- (0.6) Preparing for second (working) interview (task 0.6)
- Thursday, 17 December, 2009
- (0.7) Recruitment (incl preparation) (task 0.6)
- (0.1) Admin (task 0.1)
- Friday, 18 December, 2009
- (0.1) Recruitment: offer made (task 0.6)
- (0.4) Response to JISC Deposit Expose and Discover call (task 0.1)
- (0.1) General admin (task 0.1)
- Wednesday, 23 December, 2009
- (0.5) Meeting with John Pybus (task 1.0)